Replacement due to projected end of asset lifecycle.
RR.01Affolter Neighborhood Park
Progress
- Not started
- Financial planning
- Planning
- Implementation
- Continuous
Tasks
What's left to do?
- 2028
Picnic Table Replacement
- 2031
Playground Replacement
- 2034
Replace Trash Cans, Benches, Park Entry Sign and Handball Wall
Replacement due to projected end of asset lifecycle.
- 2036
Booster Pump Replacement
Replacement due to projected end of asset lifecycle.
- 2038
Sport Court Lighting Replacement, Tennis Court Renewal, Ballfield Renewal
Replacement due to projected end of asset lifecycle.
- 2048
Basketball Court Renewal
Replacement due to projected end of asset lifecycle.
What are we doing?
- 2025
Tennis Court Resurfacing
What has been done?
- 03/10/2022
New shelter/restroom/ballfield and site improvements
- 11/13/2015
Playground and New Surfacing Installation
Replacement due to projected end of asset lifecycle.