Lead paragraph

A neighborhood park planned to serve residential expansion in the area south of Clover Basin Drive and is recommended to be developed. Together with Dry Creek Greenway, this site is important to serving gap area S2.

Tasks

What's left to do?

  • Todo2030

    Bike Repair Station Replacement

    Replacement due to projected end of asset lifecycle.

  • Todo2035

    Signage and Site Furnishing Replacement

    Replacement due to projected end of asset lifecycle. Furnishings to include: Bench, Picnic Table, Trash Can, Recycle Cans, BBQ.

  • Todo2050

    Park Shelter Renewal

    Replacement due to projected end of asset lifecycle.

What has been done?

  • Done12/12/2024

    New Park Construction

Read more

Summary and contacts

  • Park Access Gap Area

    S-2