Replacement due to projected end of asset lifecycle.
RR.14Dry Creek Community Park
Progress
- Not started
- Financial planning
- Planning
- Implementation
- Continuous
Tasks
What's left to do?
- 2031
Signage and Site Furnishing Replacement
- 2032
Accent Lighting Replacement
- 2041
Pumphouse Renewal
Replacement due to projected end of asset lifecycle.
- 2042
Playground Replacement
Replacement due to projected end of asset lifecycle.
- 2047
Restroom Renewal
Replacement due to projected end of asset lifecycle.
- 2047
Parking Lot Lighting Replacement
Replacement due to projected end of asset lifecycle.
What has been done?
- 17.01.2025
Sports Field Lighting
- 17.01.2025
Refurbishing Sports Fields
Replacement due to projected end of asset lifecycle. Furnishings to include: Bench, Bike Rack, Picnic Table, Trash Can