Replacement due to projected end of asset lifecycle.
RR.25Lanyon Neighborhood Park
Progress
- Not started
- Financial planning
- Planning
- Implementation
- Continuous
Tasks
What's left to do?
- 2028
Park Entrance Sign replacement
- 2028
Site Furnishing Replacement
- 2028
Path Light Renewal
- 2033
Site Furnishing Replacement
Replacement due to projected end of asset lifecycle. Furnishings to include: Picnic Table, Bench, BBQ.
- 2033
Ballfield Renewal
Replacement due to projected end of asset lifecycle.
- 2038
Restroom Renewal
Replacement due to projected end of asset lifecycle.
What are we doing?
- 2025
Park Cooling Feature
What has been done?
- 10/07/2016
Playground Replacement
Replacement due to projected end of asset lifecycle. Furnishings to include: Trash Can, Picnic Table.