Replacement due to projected end of asset lifecycle.
RR.05Carr Neighborhood Park
Progress
- Not started
- Financial planning
- Planning
- Implementation
- Continuous
Tasks
What's left to do?
- 2025
Lighting Updates (park lighting, path lighting, sports court)
- 2026
Tennis Court Surfacing
- 2028
Site Furnishing Replacement: Bench, Trash Can
Replacement due to projected end of asset lifecycle.
- 2029
Ballfield Renewal
Replacement due to projected end of asset lifecycle.
- 2030
Site Furnishing Replacement: Bench
Replacement due to projected end of asset lifecycle.
- 2030
Park Exterior Fencing Replacement
- 2031
Site Furnishing Replacement: BBQ, Recycle Cans
Replacement due to projected end of asset lifecycle.
- 2035
Hockey Rink Renewal
Replacement due to projected end of asset lifecycle.
- 2050
Playground Renewal
Replacement due to projected end of asset lifecycle.
What has been done?
- 05/18/2020
Playground Replacement
- 03/28/2017
New Shelter and Restroom
Replacement due to projected end of asset lifecycle.