Replacement due to projected end of asset lifecycle.
RR.17Garden Acres Community Park
Progress
- Not started
- Financial planning
- Planning
- Implementation
- Continuous
Tasks
What's left to do?
- 2024
Parking Lot Lighting
- 2026
Sports Field Lighting Replacement
- 2034
Dugout, Score Booth and Shelter Renewal
Replacement due to projected end of asset lifecycle.
- 2034
Ballfield Fence, Rail and Gate Renewal
Replacement due to projected end of asset lifecycle.
- 2034
Cricket Pitch Renewal
Replacement due to projected end of asset lifecycle.
- 2038
Signage & Site Furnishing Replacement
Replacement due to projected end of asset lifecycle. Furnishings to include: Bench, Bike Rack, Picnic Table, Trash Can,
- 2039
Maintenance Building and Restroom Renewal
Replacement due to projected end of asset lifecycle.
- 2043
Pumphouse Renewal
Replacement due to projected end of asset lifecycle.
- 2048
Ballfield Renewal
Replacement due to projected end of asset lifecycle.
- 2048
Path Lighting Replacement
Replacement due to projected end of asset lifecycle.
What are we doing?
- 4/3/2026
Pedestrian Bridge Replacement
What has been done?
- 02/06/2019
Park Renewal
- 03/14/2018
Pump House
Replacement due to projected end of asset lifecycle.