The signage updates at this park were delayed to align with the City of Longmont’s new signage branding standards, which were under development from 2022 and finalized in 2024. Now that these standards are complete, updated signage will be implemented in parks scheduled for renewal and in locations where existing signs are in poor condition and due for replacement.
The site furnishings were originally identified for replacement based on asset age, but they were not replaced at that time as they did not present safety concerns and were found to be in acceptable condition with remaining useful life. They will continue to be assessed annually, and replacement funding will be requested as their condition warrants.
Replacement due to projected end of asset lifecycle. An analysis is underway to determine if funding may be available in the upcoming CIP to renovate this park restroom.