RR.23Kanemoto Neighborhood Park

Progress

  • Not started
  • Financial planning
  • Planning
  • Implementation
  • Continuous

Tasks

What's left to do?

  • Todo2024

    Site Furnishing Replacement

    Although these site furnishings were originally identified for replacement based on asset age, they were not replaced at that time as they did not present safety concerns and were found to be in acceptable condition with remaining useful life. They will continue to be assessed annually, and replacement funding will be requested as their condition warrants.

  • Todo2028

    Path Lighting Renewal

    Replacement due to projected end of asset lifecycle.

  • Todo2034

    Volleyball Court Renewal

    Replacement due to projected end of asset lifecycle.

  • Todo2043

    Shelter Renewal

    Replacement due to projected end of asset lifecycle.

  • Todo2044

    Sports Court Lighting Renewal

    Replacement due to projected end of asset lifecycle.

  • Todo2046

    Pagoda Renewal

    Replacement due to projected end of asset lifecycle.

What has been done?

  • Done06/10/2016

    Playground Replacement

  • Done04/25/2016

    Tower of Compassion Renovation

  • Done05/05/2015

    Pump Station Replacement

Read more

Summary and contacts

  • Park Renewal

    Level 3
Information updated 07/21/2025