Build out the connections stated in the enhanced multi-use corridor (EMUC) plan.

Description

The City is continuing to expand Enhanced Multi-Use Corridors through partnering with RTD on a new, bus rapid transit station and on-street facility, finalizing design on the Coffman Street Busway/Multimodal Corridor and designing the Longmont 1st and Main Station later this year.

Summary and contacts

Base Strategies

Implement

Initiation Period

  • Cost

    $100,000 <= $$ =< $1,000,000

Contact persons

  • Kyle Haworth
    Traffic Engineering Administrator
    Public Works and Engineering
Information updated 08/28/2023